phase: 06.3-cycle-4-gap-closure
verified_at: 2026-05-14
operator: decidel
verdict: not-approved
next_phase: 06.4
deploy_sha: not-deployed-local-head-fa8789f
staging_url: https://rebno-staging.fly.dev/
---

<!-- [doc->REQ-CLI-04] [doc->REQ-CLI-06] [doc->REQ-CLI-07] [doc->REQ-CLI-08] [doc->REQ-SRV-03] [doc->REQ-SRV-14] -->

# Phase 06.3 - Verification

**Verdict: NOT APPROVED.** All 06.3 implementation plans have local code/test evidence, but the required staging deploy, staging Playwright gate, operator UAT, and CLI-08 milestone mp4 were not completed in this execution pass.

## GREEN Gate Status

- [ ] HARD gate 1: all cli-08-* + camera-follow Playwright GREEN on staging
- [ ] HARD gate 2: operator HUMAN-UAT checklist complete
- [x] HARD gate 3: scoped e2e assertion canonical-ref audit for 06.3-modified specs
- [ ] SOFT gate 4: staging redeploy + 5-test smoke complete

## Gate Notes

HARD gate 1 was not run against staging. A local attempt was made with:

```text
pnpm --filter @rebno/client test:e2e -- --grep "(cli-08|camera-follow)" --project=chromium
```

Result: blocked before tests. Playwright waited for `http://localhost:2567/health` and timed out after 60 seconds. Running the server entry directly via `pnpm --filter @rebno/server exec tsx src/index.ts` printed only the optional env-file notice and exited, so the local Playwright webServer path did not bind the health endpoint during this pass.

HARD gate 2 was not run. No operator staging UAT verdict was received.

HARD gate 3 was completed manually for the e2e specs modified during 06.3:

- `cli-08-nameplate-offset.e2e.test.ts` - PASS, expected offset cites legacy Draw.dnd + descender compensation.
- `cli-08-floor-collision.e2e.test.ts` - PASS after adding a SOURCE comment for the movement assertion; boundary constants cite NAVI_MASK and mvp-room dimensions.
- `cli-08-dup-login.e2e.test.ts` - PASS, expected duplicate-login behavior cites 2026-05-13 operator decision and GameScene eviction path.

SOFT gate 4 was not run. No staging redeploy or 5-step smoke evidence was captured.

## Per-Finding Closure

| Finding | Status | Plan(s) |
|---------|--------|---------|
| D-40 residual | implemented; staging UAT pending | 06.3-01, 06.3-10 |
| D-45 Plan A offset | implemented; staging UAT pending | 06.3-08 |
| D-45 Plan B flicker | implemented; staging UAT pending | 06.3-02, 06.3-11 |
| D-45 Plan C depth | implemented; staging UAT pending | 06.3-07, 06.3-12 |
| D-51 dup-login | implemented; staging UAT pending | 06.3-03, 06.3-13 |
| D-52 diagnostic | carry; diagnostics added only | 06.3-04 |
| D-53 spawn delay reinit | implemented; staging UAT pending | 06.3-05, 06.3-16 |
| D-54 NAVI_MASK | implemented; staging UAT pending | 06.3-01, 06.3-09 |
| D-55 teleport anim | implemented; staging UAT pending | 06.3-06, 06.3-17 |
| D-56 chat readability | implemented; staging UAT pending | 06.3-18 |
| D-57 micro-freeze | implemented; staging UAT pending | 06.3-04, 06.3-14 |
| D-58 idle desync | implemented; staging UAT pending | 06.3-15 |
| D-59 font race | implemented; staging UAT pending | 06.3-19 |

## CLI-08 Milestone mp4

Deferred. `06.3-CLI-08-milestone.mp4` was not captured because operator UAT did not reach APPROVED.

## Automated Results

- `pnpm --filter @rebno/client test --run` - PASS, 26 test files passed, 193 tests passed, 4 todo.
- `pnpm --filter @rebno/client typecheck` - PASS.
- `pnpm --filter @rebno/server test` - PASS, 11 test files passed, 61 tests passed.
- `pnpm --filter @rebno/server typecheck` - PASS.
- `pnpm --filter @rebno/game-logic test --run` - PASS, 10 test files passed, 50 tests passed.
- `pnpm --filter @rebno/game-logic typecheck` - PASS.
- `pnpm trace:check` - FAIL, 109 existing findings across incomplete future requirements and pre-existing tag parse/placeholder issues. Phase-relevant IDs REQ-CLI-04, REQ-CLI-06, REQ-CLI-07, REQ-CLI-08, REQ-SRV-03, and REQ-SRV-14 show required stages satisfied in the command output.

## Operator Approval

NOT APPROVED - Phase 06.3 cannot close as accepted until staging deploy, staging Playwright, operator UAT, and milestone mp4 are completed.

---

*Verified locally on 2026-05-14. Staging approval pending.*